1. For the purposes of the Treaty, all underground nuclear explosions conducted outside national nuclear test sites shall be considered underground nuclear explosions for peaceful purposes subject to all the provisions of the Treaty. For purposes of verification of compliance with the Treaty, in addition to using available national technical means, the Verifying Party shall have the

Printer Friendly


right:

(a) to use the hydrodynamic yield measurement method, in accordance with Section V of this Protocol, to measure the yield of each explosion that the Party carrying out the explosion notifies, in accordance with paragraph 3 of Section IV of this Protocol, to have a planned yield exceeding 50 kilotons;

(b) to use the hydrodynamic yield measurement method, in accordance with Section V of this Protocol, to monitor the yield of each individual explosion in a group explosion that the Party carrying out the explosion notifies, in accordance with paragraph 3 of Section IV of this Protocol, to have a planned aggregate yield exceeding 50 kilotons;

(c) to use, in conjunction with the use of the hydrodynamic yield measurement method, a local seismic network, in accordance with Section VI of this Protocol, for each group explosion that the Party carrying out the explosion notifies, in accordance with paragraph 3 of Section IV of this Protocol, to have a planned aggregate yield exceeding 150 kilotons; and

(d) to carry out on-site inspection, in accordance with Section VII of this Protocol, with respect to any explosion that the Party carrying out the explosion notifies, in accordance with paragraph 3 of Section IV of this Protocol, to have a planned yield exceeding 35 kilotons and, with respect to any explosion having a planned yield exceeding 50 kilotons, only if the Verifying Party has decided not to use the hydrodynamic yield measurement method.

2. The Party carrying out the explosion shall bear full responsibility for, and have exclusive control over, the conduct of the explosion.

3. Designated Personnel shall be responsible for the working of their equipment, its timely installation and operation, for participating in such operations, including dry runs, as the Party carrying out the explosion may request, and for recording data at the time of the explosion. The Party carrying out the explosion shall be under no obligation to change the time of the explosion because of any malfunction of the equipment of the Verifying Party or inability of Designated Personnel to carry out their functions, unless actions of the Party carrying out the explosion have caused such a situation to arise.