1. In carrying out on-site inspection, the Verifying Party shall have the right to confirm the validity of the geological, geophysical, and geometrical information provided in accordance with paragraphs 4 and 9 of Section IV of this Protocol, in accordance with the following procedures:

Printer Friendly


(a) the Testing Party shall provide Designated Personnel, upon their arrival at the test site, with the results of any studies of core samples and rock fragments extracted from each emplacement hole and any exploratory holes and tunnels, and the results of logging and geodetic measurements carried out in each emplacement hole and any exploratory holes and tunnels, relevant to the geology and geophysics of the emplacement medium, if the Testing Party carried out such studies and measurements;

(b) using their own equipment and under observation of personnel of the Testing Party, Designated Personnel shall have the right to carry out:

(i) if an emplacement hole is vertical, in the emplacement hole, from the end of the hole to the entrance to the hole, gamma-gamma, gamma, neutron, electrical resistivity, magnetic susceptibility, gravity, acoustic, television, and caliper logging, and measurements of the depth and cross section of the emplacement hole, as well as measurements to determine the location and volume of voids, using, in a non- destructive way, such methods as electromagnetic measurements, radar, and acoustic sounding; and

(ii) if an emplacement hole is horizontal, in the holes specified in subparagraph (d)(ii) of this paragraph, and in the emplacement hole in the regions extending from each end of the emplacement hole to a point located 300 meters from the corresponding emplacement point in the direction of the entrance to the emplacement hole, gamma-gamma, gamma, neutron, electrical resistivity, magnetic susceptibility, gravity, acoustic, and caliper logging, and measurements of the length and cross section of the emplacement hole, as well as measurements to determine the location and volume of voids, using, in a non-destructive way, such methods as electromagnetic measurements, radar, and acoustic sounding;

(c) all logging and geometrical measurement data obtained by Designated Personnel in accordance with subparagraph (b) of this paragraph, including calibration data, shall be duplicated, and a copy of these data shall be provided to personnel of the Testing Party prior to the departure from the test site of Designated Personnel who have carried out those measurements. Calibration data shall include information needed to confirm the sensitivity of logging equipment under the conditions in which it is used;

(d) Designated Personnel shall have the right to receive:

(i) if an emplacement hole is vertical, core samples or rock fragments, at the option of Designated Personnel, extracted from the emplacement hole at 10 depths specified by Designated Personnel, plus one additional depth for every complete 50-meter distance between the uppermost and lowest emplacement points. The total volume of core samples or rock fragments extracted at each of the specified depths shall be no less than 400 cubic centimeters and no more than 3000 cubic centimeters, unless the Parties otherwise agree; and

(ii) if an emplacement hole is horizontal, core samples or rock fragments, at the option of Designated Personnel, from the emplacement hole in the regions extending from each end of the emplacement hole to a point located 300 meters from the corresponding emplacement point in the direction of the entrance to the emplacement hole. Core samples shall be extracted during drilling from each of five holes drilled at stations in the emplacement hole, specified by Designated Personnel. These five stations shall be separated from each other by no less than 15 meters. At each station the hole shall be drilled in a direction specified by Designated Personnel, except that at each station within 65 meters of each emplacement point the Testing Party shall have the right to exclude two 90-degree sectors separated by a sector of 90 degrees. The diameter of each drilled hole shall be no less than 0.09 meters and no more than 0.15 meters, and the depth of each hole shall be no more than the diameter of the emplacement hole at that station. Core samples shall be extracted at locations specified by Designated Personnel along the drilled hole. Rock fragments shall be extracted from the walls of the emplacement hole at five stations specified by Designated Personnel. The total volume of core samples or rock fragments extracted at each station shall be no less than 400 cubic centimeters and no more than 3000 cubic centimeters, unless the Parties otherwise agree.

(e) core samples or rock fragments, at the option of Designated Personnel, shall be extracted, in accordance with subparagraph (d) of this paragraph, by personnel of the Testing Party, under observation of Designated Personnel, or by Designated Personnel, at the option of the Testing Party;

(f) if the Testing Party does not extract core samples or rock fragments in accordance with subparagraph (d) of this paragraph, Designated Personnel shall have the right to do so, using their own equipment and under observation of personnel of the Testing Party;

(g) if, prior to arrival of Designated Personnel at the test site, the Testing Party has cased more than a total of 20 meters within any 100-meter segment of a vertical emplacement hole in the region extending from the end of the emplacement hole to a point 300 meters from the planned emplacement point in the direction of the entrance to the emplacement hole, the Testing Party shall provide an uncased hole with respect to which the Verifying Party shall have the same rights as those specified for an emplacement hole in subparagraphs (b), (d), (e), and (f) of this paragraph. This uncased hole shall be located no more than 50 meters from the emplacement hole and shall have a depth no less than that of the emplacement hole. If personnel of the Testing Party, under observation of Designated Personnel, extract core samples through coring during the drilling of this uncased hole, the diameter of this hole shall be no less than 0.09 meters. If Designated Personnel, under observation of personnel of the Testing Party, extract core samples from this uncased hole following drilling, the diameter of this uncased hole shall be no less than 0.3 meters; and

(h) Designated Personnel shall have the right to retain core samples and rock fragments specified in subparagraphs (d), (e), (f), and (g) of this paragraph. Any such core samples or rock fragments shall be prepared in accordance with the procedures agreed upon by the Parties for shipment to the territory of the Verifying Party.

2. Designated Personnel shall have the right:

(a) if an emplacement hole is vertical, to observe the emplacement of each explosive canister into the emplacement hole from the time the bottom of the canister is last visible above the entrance of the emplacement hole, and to determine by direct measurement the depth of emplacement of the bottom of the canister;

(b) if an emplacement hole is horizontal, to determine by direct measurement the location of each explosive canister in the emplacement hole, and to confirm the presence of at least 10 meters of stemming, as specified in subparagraph (c)(ii) of this paragraph, in any previously stemmed tunnel that had provided access to an explosive canister, using, in a non-destructive way, such methods as electromagnetic measurements, radar, and acoustic sounding;

(c) to observe stemming of each emplacement hole:

(i) if an emplacement hole is vertical, until a solid concrete plug no less than three meters thick is installed above the explosive canister closest to the entrance to the emplacement hole; and

(ii) if an emplacement hole is horizontal, until access to any explosive canister has been prevented by installation of stemming material for a distance no less than 10 meters, including the installation of a solid concrete plug no less than three meters thick;

(d) to have access along agreed routes to the location of the test to carry out activities related to on-site inspection;

(e) to have access to their equipment associated with the carrying out of on-site inspection from the time of its transfer to Designated Personnel at the test site, until it is transferred to personnel of the Testing Party in accordance with paragraph 9(g) of Section VIII of this Protocol, unless otherwise provided in this Protocol;

(f) if an emplacement hole is vertical, to have access, for the purpose of visual inspection of the ground surface, to the area delineated by a circle having a radius of 300 meters, centered on the entrance to the emplacement hole; and

(g) if an emplacement hole is horizontal, to have access, for the purpose of visual inspection of the ground surface, to the area delineated by a circle having a radius of 300 meters, centered directly above the emplacement point of each explosive canister.

3. Designated Personnel shall have the right to obtain photographs associated with on-site inspection, which shall be taken in accordance with paragraph 12 of Section V of this Protocol, of the following:

(a) if an emplacement hole is vertical, the emplacement of each explosive canister and the stemming of the emplacement hole specified in paragraph 2(c)(i) of this Section;

(b) if an emplacement hole is horizontal, the interior of the emplacement hole within 20 meters of the emplacement point of each explosive canister, and the stemming of the emplacement hole specified in paragraph 2(c)(ii) of this Section;

(c) core samples and rock fragments, extracted in accordance with paragraphs 1 (d), 1 (e), 1 (f), and 1 (g) of this Section, the equipment and activities associated with extracting such samples, as well as the interior of the emplacement hole, if the emplacement hole is horizontal, at the stations where core samples and rock fragments were extracted; and

(d) with the agreement of the Testing Party, other activities of Designated Personnel directly related to on-site inspection.

4. In no case shall the cumulative delay resulting from the photographic process specified in paragraph 3 of this Section exceed two hours for each of the operations specified in paragraph 3 of this Section, unless the Parties otherwise agree, except that stemming shall not be interrupted as a result of the photographic process.

5. All on-site inspection activities shall be carried out in accordance with the coordinated schedule. Designated Personnel shall have the right, within a period not to exceed 15 days, to carry out logging and coring activities specified in paragraph 1 of this Section, unless the Parties otherwise agree and so specify in the coordinated schedule. These activities shall be completed no less than one day prior to the beginning of emplacement of explosives. Upon completion of the activities specified in paragraph 1 of this Section, Designated Personnel shall depart the territory of the Testing Party, except that Designated Personnel who will also participate in the activities specified in paragraph 2 of this Section shall remain at the test site, if the Parties decide that this is required by the coordinated schedule. Otherwise, Designated Personnel shall depart the territory of the Testing Party or, if agreed by the Parties, they may depart to another point within the territory of the Testing Party. All Designated Personnel who will carry out the activities specified in paragraph 2 of this Section shall arrive at the test site in accordance with the coordinated schedule, but no less than three days prior to the date specified by the Testing Party for the beginning of these activities.

6. The number of Designated Personnel carrying out the activities specified in paragraph 1 of this Section shall not exceed 23 at any time. The number of Designated Personnel carrying out activities specified in paragraphs 2(a), 2(b), and 2(c) of this Section shall not exceed five at any time. At least one individual fluent in the language of the Testing Party shall be among Designated Personnel. Section VII. On-Site Inspection

1. In carrying out on-site inspection, the Verifying Party shall have the right to confirm the validity of the geological, geophysical, and geometrical information provided in accordance with paragraphs 4 and 9 of Section IV of this Protocol, in accordance with the following procedures:

(a) the Testing Party shall provide Designated Personnel, upon their arrival at the test site, with the results of any studies of core samples and rock fragments extracted from each emplacement hole and any exploratory holes and tunnels, and the results of logging and geodetic measurements carried out in each emplacement hole and any exploratory holes and tunnels, relevant to the geology and geophysics of the emplacement medium, if the Testing Party carried out such studies and measurements;

(b) using their own equipment and under observation of personnel of the Testing Party, Designated Personnel shall have the right to carry out:

(i) if an emplacement hole is vertical, in the emplacement hole, from the end of the hole to the entrance to the hole, gamma-gamma, gamma, neutron, electrical resistivity, magnetic susceptibility, gravity, acoustic, television, and caliper logging, and measurements of the depth and cross section of the emplacement hole, as well as measurements to determine the location and volume of voids, using, in a non- destructive way, such methods as electromagnetic measurements, radar, and acoustic sounding; and

(ii) if an emplacement hole is horizontal, in the holes specified in subparagraph (d)(ii) of this paragraph, and in the emplacement hole in the regions extending from each end of the emplacement hole to a point located 300 meters from the corresponding emplacement point in the direction of the entrance to the emplacement hole, gamma-gamma, gamma, neutron, electrical resistivity, magnetic susceptibility, gravity, acoustic, and caliper logging, and measurements of the length and cross section of the emplacement hole, as well as measurements to determine the location and volume of voids, using, in a non-destructive way, such methods as electromagnetic measurements, radar, and acoustic sounding;

(c) all logging and geometrical measurement data obtained by Designated Personnel in accordance with subparagraph (b) of this paragraph, including calibration data, shall be duplicated, and a copy of these data shall be provided to personnel of the Testing Party prior to the departure from the test site of Designated Personnel who have carried out those measurements. Calibration data shall include information needed to confirm the sensitivity of logging equipment under the conditions in which it is used;

(d) Designated Personnel shall have the right to receive:

(i) if an emplacement hole is vertical, core samples or rock fragments, at the option of Designated Personnel, extracted from the emplacement hole at 10 depths specified by Designated Personnel, plus one additional depth for every complete 50-meter distance between the uppermost and lowest emplacement points. The total volume of core samples or rock fragments extracted at each of the specified depths shall be no less than 400 cubic centimeters and no more than 3000 cubic centimeters, unless the Parties otherwise agree; and

(ii) if an emplacement hole is horizontal, core samples or rock fragments, at the option of Designated Personnel, from the emplacement hole in the regions extending from each end of the emplacement hole to a point located 300 meters from the corresponding emplacement point in the direction of the entrance to the emplacement hole. Core samples shall be extracted during drilling from each of five holes drilled at stations in the emplacement hole, specified by Designated Personnel. These five stations shall be separated from each other by no less than 15 meters. At each station the hole shall be drilled in a direction specified by Designated Personnel, except that at each station within 65 meters of each emplacement point the Testing Party shall have the right to exclude two 90-degree sectors separated by a sector of 90 degrees. The diameter of each drilled hole shall be no less than 0.09 meters and no more than 0.15 meters, and the depth of each hole shall be no more than the diameter of the emplacement hole at that station. Core samples shall be extracted at locations specified by Designated Personnel along the drilled hole. Rock fragments shall be extracted from the walls of the emplacement hole at five stations specified by Designated Personnel. The total volume of core samples or rock fragments extracted at each station shall be no less than 400 cubic centimeters and no more than 3000 cubic centimeters, unless the Parties otherwise agree.

(e) core samples or rock fragments, at the option of Designated Personnel, shall be extracted, in accordance with subparagraph (d) of this paragraph, by personnel of the Testing Party, under observation of Designated Personnel, or by Designated Personnel, at the option of the Testing Party;

(f) if the Testing Party does not extract core samples or rock fragments in accordance with subparagraph (d) of this paragraph, Designated Personnel shall have the right to do so, using their own equipment and under observation of personnel of the Testing Party;

(g) if, prior to arrival of Designated Personnel at the test site, the Testing Party has cased more than a total of 20 meters within any 100-meter segment of a vertical emplacement hole in the region extending from the end of the emplacement hole to a point 300 meters from the planned emplacement point in the direction of the entrance to the emplacement hole, the Testing Party shall provide an uncased hole with respect to which the Verifying Party shall have the same rights as those specified for an emplacement hole in subparagraphs (b), (d), (e), and (f) of this paragraph. This uncased hole shall be located no more than 50 meters from the emplacement hole and shall have a depth no less than that of the emplacement hole. If personnel of the Testing Party, under observation of Designated Personnel, extract core samples through coring during the drilling of this uncased hole, the diameter of this hole shall be no less than 0.09 meters. If Designated Personnel, under observation of personnel of the Testing Party, extract core samples from this uncased hole following drilling, the diameter of this uncased hole shall be no less than 0.3 meters; and

(h) Designated Personnel shall have the right to retain core samples and rock fragments specified in subparagraphs (d), (e), (f), and (g) of this paragraph. Any such core samples or rock fragments shall be prepared in accordance with the procedures agreed upon by the Parties for shipment to the territory of the Verifying Party.

2. Designated Personnel shall have the right:

(a) if an emplacement hole is vertical, to observe the emplacement of each explosive canister into the emplacement hole from the time the bottom of the canister is last visible above the entrance of the emplacement hole, and to determine by direct measurement the depth of emplacement of the bottom of the canister;

(b) if an emplacement hole is horizontal, to determine by direct measurement the location of each explosive canister in the emplacement hole, and to confirm the presence of at least 10 meters of stemming, as specified in subparagraph (c)(ii) of this paragraph, in any previously stemmed tunnel that had provided access to an explosive canister, using, in a non-destructive way, such methods as electromagnetic measurements, radar, and acoustic sounding;

(c) to observe stemming of each emplacement hole:

(i) if an emplacement hole is vertical, until a solid concrete plug no less than three meters thick is installed above the explosive canister closest to the entrance to the emplacement hole; and

(ii) if an emplacement hole is horizontal, until access to any explosive canister has been prevented by installation of stemming material for a distance no less than 10 meters, including the installation of a solid concrete plug no less than three meters thick;

(d) to have access along agreed routes to the location of the test to carry out activities related to on-site inspection;

(e) to have access to their equipment associated with the carrying out of on-site inspection from the time of its transfer to Designated Personnel at the test site, until it is transferred to personnel of the Testing Party in accordance with paragraph 9(g) of Section VIII of this Protocol, unless otherwise provided in this Protocol;

(f) if an emplacement hole is vertical, to have access, for the purpose of visual inspection of the ground surface, to the area delineated by a circle having a radius of 300 meters, centered on the entrance to the emplacement hole; and

(g) if an emplacement hole is horizontal, to have access, for the purpose of visual inspection of the ground surface, to the area delineated by a circle having a radius of 300 meters, centered directly above the emplacement point of each explosive canister.

3. Designated Personnel shall have the right to obtain photographs associated with on-site inspection, which shall be taken in accordance with paragraph 12 of Section V of this Protocol, of the following:

(a) if an emplacement hole is vertical, the emplacement of each explosive canister and the stemming of the emplacement hole specified in paragraph 2(c)(i) of this Section;

(b) if an emplacement hole is horizontal, the interior of the emplacement hole within 20 meters of the emplacement point of each explosive canister, and the stemming of the emplacement hole specified in paragraph 2(c)(ii) of this Section;

(c) core samples and rock fragments, extracted in accordance with paragraphs 1 (d), 1 (e), 1 (f), and 1 (g) of this Section, the equipment and activities associated with extracting such samples, as well as the interior of the emplacement hole, if the emplacement hole is horizontal, at the stations where core samples and rock fragments were extracted; and

(d) with the agreement of the Testing Party, other activities of Designated Personnel directly related to on-site inspection.

4. In no case shall the cumulative delay resulting from the photographic process specified in paragraph 3 of this Section exceed two hours for each of the operations specified in paragraph 3 of this Section, unless the Parties otherwise agree, except that stemming shall not be interrupted as a result of the photographic process.

5. All on-site inspection activities shall be carried out in accordance with the coordinated schedule. Designated Personnel shall have the right, within a period not to exceed 15 days, to carry out logging and coring activities specified in paragraph 1 of this Section, unless the Parties otherwise agree and so specify in the coordinated schedule. These activities shall be completed no less than one day prior to the beginning of emplacement of explosives. Upon completion of the activities specified in paragraph 1 of this Section, Designated Personnel shall depart the territory of the Testing Party, except that Designated Personnel who will also participate in the activities specified in paragraph 2 of this Section shall remain at the test site, if the Parties decide that this is required by the coordinated schedule. Otherwise, Designated Personnel shall depart the territory of the Testing Party or, if agreed by the Parties, they may depart to another point within the territory of the Testing Party. All Designated Personnel who will carry out the activities specified in paragraph 2 of this Section shall arrive at the test site in accordance with the coordinated schedule, but no less than three days prior to the date specified by the Testing Party for the beginning of these activities.

6. The number of Designated Personnel carrying out the activities specified in paragraph 1 of this Section shall not exceed 23 at any time. The number of Designated Personnel carrying out activities specified in paragraphs 2(a), 2(b), and 2(c) of this Section shall not exceed five at any time. At least one individual fluent in the language of the Testing Party shall be among Designated Personnel.